Tuesday, November 10, 2009

Dedication To Deceased Mother At Wedding

Masonry

Today the masons were again at work to catch up on the previous day, two teams entered the building.

you are well:

level 10 clock
as 17.30 clock





The clinker bricks have also come.











supervisor meeting:
Our new site manager has been presented today, and was super prepared.
Open questions could be clarified and operating points were implemented promptly.
We have received the schedule, how to do it until the end of February next. The
own work can now be properly planned.
The target award is scheduled for next Wednesday 15:30 clock.

own performance in sliding wall
Have I discussed today evening with Uli, as the 3 walls can be implemented tomorrow, the material is ordered.

0 comments:

Post a Comment